๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Hwy 21 Truck Stop
4070 Williams Rd, Mustang Ridge, TX 78610, Mustang Ridge, TX, 78610
Construction50%
๐Project Metrics
TDLR #TABS2022018647$800K
Project Value
9,020
Square Feet
$89/sqft
Cost/SqFt
3y 9mo
Duration
Registered:May 10, 2022
Start:Sep 1, 2022
Target:May 1, 2026
Remaining:123 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
A NEW CONSTRUCTION OF A TRUCK STOP, 9,020 S.F. WITH 5 CAR MPDs AND 3 TRUCK'S.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 10, 2022
Construction Start
September 1, 2022
Expected Completion
May 1, 2026
๐Related Projects
๐คSame Owner
$2.0M totalProperty Owner
๐ค
Poco Loco Group LLC
Contact: Asifali Karowalia
2 projects ยท $2.0M
View all projects
1095 Windy Hill Rd, Kyle, Texas 78640
Design Firm
๐๏ธ
Tchen Architect
4 projects ยท $2.0M
View company profile
1303 Elm forest Dr, Cedar park, Texas 78613