โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

New Silsbee Fire Station, Hardin County Emergency Services District 6

1205 N 5th Street, Silsbee, TX 77656, Silsbee, TX, 77656
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022024146
$5.4M
Project Value
23,333
Square Feet
$231/sqft
Cost/SqFt
1y 4mo
Duration
Registered:Jul 20, 2022
Start:Aug 22, 2022
Target:Dec 25, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

New fire station with an unfinished second floor.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 20, 2022
Construction Start
August 22, 2022
Expected Completion
December 25, 2023