San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement is a new construction project at 504 Harvill St, Sinton, in San Patricio County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish May 2023 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $1.0M across about 3,500 sq ft.
- Estimated project value
- $1.0M
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 3,500 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $286/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 7 months
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
4 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordReview complete · TDLR filing
The filing records completion of the accessibility review.
Same day as the preceding date shown.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
37 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
212 days after the preceding date shown.
Source: TDLR filing
View source record
Review Complete
Design review complete, construction may proceed
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 78387 (Sinton)
One email per change. Unsubscribe in one click. Privacy.
San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement is a New Construction project located at 504 Harvill St, Sinton, TX 78387 in Sinton, Texas. The project has an estimated value of $1.0M covering 3,500 sq ft. San Patrcio County, TX is the property owner and Ardurra is the design firm of record. The project was registered with TDLR on August 25, 2022.
Frequently Asked Questions
What is San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement?
San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement is a new construction project at 504 Harvill St in Sinton, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Construction a 3,500 sf stand alone pre-engineered metal bldg.
Is San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement open in Sinton?
San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement was scheduled to finish construction in May 2023 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.
Where is San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement located?
San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement is located at 504 Harvill St, Sinton, TX, 78387, in San Patricio County.
Who is the owner or developer of San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement?
San Patrcio County, TX is the property owner/developer of record for San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement, per its TDLR project registration.
Who is the architect or design firm for San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement?
Ardurra is the design firm of record for San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement, according to its TDLR filing.
How much does San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement cost and how big is it?
San Patricio County Warehouse Addition & Juvenile Detention Center Roofing Replacement has an estimated construction value of $1.0M and approximately 3,500 square feet (about $286/sqft), based on its TDLR filing.
Scope of Work
Construction a 3,500 sf stand alone pre-engineered metal bldg.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
504 Harvill St, Sinton, TX, 78387
Related Projects
Watch all construction in 78387 (Sinton)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Sinton?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.