๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
New Braunfels Utilities Trinity Membrane Treatment Plant & Pump Station Expansion
3295 Westpointe Drive, New Braunfels, TX 78132, New Braunfels, TX, 78132
Completed100%
๐Project Metrics
TDLR #TABS2022027477$540K
Project Value
940
Square Feet
$574/sqft
Cost/SqFt
1y 5mo
Duration
Registered:Aug 31, 2022
Start:Dec 19, 2022
Target:Apr 28, 2024
๐
Project Closed
Project has been completed and closed
๐Scope of Work
new VFD building to house electrical VFDs for hte booster pump station.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 31, 2022
Project Closed
April 28, 2024
Construction Start
December 19, 2022
Expected Completion
April 28, 2024
๐Related Projects
๐คSame Owner
$3.0M totalProperty Owner
๐ค
New Braunfels Utilities
Contact: Ashley
2 projects ยท $3.0M
View company profile
263 Main Plaza, New Braunfels, Texas 78130