📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.

New Office Warehouse Facility

10350 Railroad, El Paso, TX 79904, El Paso, TX, 79904
Construction50%

📊Project Metrics

TDLR #TABS2023002563
$868K
Project Value
10,000
Square Feet
$87/sqft
Cost/SqFt
6 months
Duration
Registered:Oct 6, 2022
Start:Oct 17, 2022
Target:Apr 1, 2023
📝

Review Complete

Design review complete, construction may proceed

📋Scope of Work

New single story pre-engineered Bulter building and 1200 interior office and restrooms.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
October 6, 2022
Review Complete
October 6, 2022
Construction Start
October 17, 2022
Expected Completion
April 1, 2023