Project intelligenceTDLR TABS2023005208Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

MLK Blvd Ph 3 Improvements

MLK from Trunk St to RB Cullum, Dallas, TX, 75210

Construction complete · Dec 2022Project Closed

MLK Blvd Ph 3 Improvements is a renovation/alteration project at MLK from Trunk St to RB Cullum, Dallas, in Dallas County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Dec 2022). The project has an estimated value of $404K across about 100 sq ft.

Estimated project value
$404K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
100 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$4.04K/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
2y 10mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Mar 1, 20201,019 days across supplied datesDec 15, 2022

4 timeline dates shown.

  1. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Source: TDLR filing

    View source record
  2. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    985 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Project closed · TDLR filing

    The project record was closed in TDLR.

    34 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75210 (Dallas)

One email per change. Unsubscribe in one click. Privacy.

MLK Blvd Ph 3 Improvements is a Renovation/Alteration project located at MLK from Trunk St to RB Cullum, Dallas, TX 75210 in Dallas, Texas. The project has an estimated value of $404K covering 100 sq ft. City of Dallas is the property owner and Freese and Nichols, Inc. is the design firm of record. The project was registered with TDLR on November 11, 2022.

Frequently Asked Questions

What is MLK Blvd Ph 3 Improvements?

MLK Blvd Ph 3 Improvements is a renovation/alteration project at MLK from Trunk St to RB Cullum in Dallas, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Intersection and crosswalk improvements.

Is MLK Blvd Ph 3 Improvements open in Dallas?

Construction on MLK Blvd Ph 3 Improvements is complete — TDLR records show the project passed its required accessibility inspection in Dec 2022. The building is finished and very likely open.

Where is MLK Blvd Ph 3 Improvements located?

MLK Blvd Ph 3 Improvements is located at MLK from Trunk St to RB Cullum, Dallas, TX, 75210, in Dallas County.

Who is the owner or developer of MLK Blvd Ph 3 Improvements?

City of Dallas is the property owner/developer of record for MLK Blvd Ph 3 Improvements, per its TDLR project registration.

Who is the architect or design firm for MLK Blvd Ph 3 Improvements?

Freese and Nichols, Inc. is the design firm of record for MLK Blvd Ph 3 Improvements, according to its TDLR filing.

How much does MLK Blvd Ph 3 Improvements cost and how big is it?

MLK Blvd Ph 3 Improvements has an estimated construction value of $404K and approximately 100 square feet (about $4.04K/sqft), based on its TDLR filing.

Scope of Work

Intersection and crosswalk improvements.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

MLK from Trunk St to RB Cullum, Dallas, TX, 75210

Location by street address

Watch all construction in 75210 (Dallas)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.