Project intelligenceTDLR TABS2023005539New Construction
Funding type

This project is privately funded, on private land for private use.

SOUTH HUB INDUSTRIAL PARK, BUILDING 3

9405 FM 812, Austin, TX, 78719

Construction complete · Mar 2024Project Closed

SOUTH HUB INDUSTRIAL PARK, BUILDING 3 is a new construction project at 9405 FM 812, Austin, in Travis County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Mar 2024). The project has an estimated value of $9.3M across about 140,230 sq ft.

Estimated project value
$9.3M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
140,230 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$66/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 2mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Nov 16, 2022485 days across supplied datesMar 15, 2024

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    60 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Project closed · TDLR filing

    The project record was closed in TDLR.

    425 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record

📰About SOUTH HUB INDUSTRIAL PARK, BUILDING 3

South HUB Industrial Park, Building 3 is a new construction shell warehouse located at 9405 FM 812 in Austin, Texas. The project occupies a site in the Pilot Knob Acres area of Travis County and stands at 140,230 square feet. The estimated cost for this development is $9,255,180, which calculates to $66 per square foot. This figure is below the county median of $125 per square foot for similar filings, though the total project cost sits above the county median for new construction projects.

The owner of record is SP5, LLC, a developer with a portfolio that includes three other TDLR-registered projects in Austin, all of which are closed. The design firm of record is Open Studio Architecture, which has handled six other registered projects across Texas, including locations in San Antonio and New Braunfels. The project was privately funded on private land for private use.

Construction Timeline and Status

Construction on the warehouse began in January 2023. The filing scheduled a completion date of March 2024, a build window of 425 days. This duration is longer than the county median scheduled build window of 304 days for new construction. The project was registered with TDLR in November 2022. TDLR closed the project file in March 2024, which marks the end of the accessibility review process for this construction. The status is listed as Project Closed.

The site is part of a broader industrial development in the area, with other registered projects nearby including Airfield 130 Industrial and MLF Operations Bldg. The local context for ZIP code 78719 includes a population of about 1,556 people and a median household income of $54,545, according to U.S. Census estimates. The area has 594 housing units, with a median owner-occupied home value of $120,800. Housing in this ZIP code is predominantly owner-occupied. The Travis County unemployment rate was 3.9 percent in July 2026, according to FRED data.

SP5, LLC’s other projects in Austin include two additional South HUB Industrial Park buildings, one valued at $7,087,608 and another at $4,326,300, both also closed. Open Studio Architecture’s other work includes the Solms Landing Retail project in New Braunfels, valued at $5,165,040, and the Redbird Plaza Retail Shell in San Antonio, valued at $4,000,000. These projects reflect the firm’s experience with commercial and retail construction in Texas. The South HUB Industrial Park, Building 3 project is now complete with its regulatory review finalized.

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78719 (Austin)

One email per change. Unsubscribe in one click. Privacy.

SOUTH HUB INDUSTRIAL PARK, BUILDING 3 is a New Construction project located at 9405 FM 812, Austin, TX 78719 in Austin, Texas. The project has an estimated value of $9.3M covering 140,230 sq ft. Owner SP5, LLC is the property owner and OPEN STUDIO ARCHITECTURE is the design firm of record. The project was registered with TDLR on November 16, 2022.

Frequently Asked Questions

Is South HUB Industrial Park, Building 3 open?

The TDLR record indicates the construction project is closed. The accessibility review process ended in March 2024. The record does not specify if the warehouse is operating or leased.

Who owns the South HUB Industrial Park, Building 3?

The owner of record is SP5, LLC. This developer has three other TDLR-registered projects in Austin, all of which are closed.

What is the square footage of the warehouse?

The project is 140,230 square feet. This is significantly larger than the county median of 12,000 square feet for new construction filings.

When was the construction completed?

The filing listed a completion date of March 2024. TDLR closed the project file in March 2024, marking the end of the review process.

What is SOUTH HUB INDUSTRIAL PARK, BUILDING 3?

SOUTH HUB INDUSTRIAL PARK, BUILDING 3 is a new construction project at 9405 FM 812 in Austin, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: NEW CONSTRUCTION SHELL WAREHOUSE

Is SOUTH HUB INDUSTRIAL PARK, BUILDING 3 open in Austin?

Construction on SOUTH HUB INDUSTRIAL PARK, BUILDING 3 is complete — TDLR records show the project passed its required accessibility inspection in Mar 2024. The building is finished and very likely open.

Where is SOUTH HUB INDUSTRIAL PARK, BUILDING 3 located?

SOUTH HUB INDUSTRIAL PARK, BUILDING 3 is located at 9405 FM 812, Austin, TX, 78719, in Travis County.

Who is the owner or developer of SOUTH HUB INDUSTRIAL PARK, BUILDING 3?

Owner SP5, LLC is the property owner/developer of record for SOUTH HUB INDUSTRIAL PARK, BUILDING 3, per its TDLR project registration.

Who is the architect or design firm for SOUTH HUB INDUSTRIAL PARK, BUILDING 3?

OPEN STUDIO ARCHITECTURE is the design firm of record for SOUTH HUB INDUSTRIAL PARK, BUILDING 3, according to its TDLR filing.

How much does SOUTH HUB INDUSTRIAL PARK, BUILDING 3 cost and how big is it?

SOUTH HUB INDUSTRIAL PARK, BUILDING 3 has an estimated construction value of $9.3M and approximately 140,230 square feet (about $66/sqft), based on its TDLR filing.

Scope of Work

NEW CONSTRUCTION SHELL WAREHOUSE

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

9405 FM 812, Austin, TX, 78719

Location by street address

Related City Permits

Building permits found at or near this location

9405 CORVALLIS DR

irrigation for lawn

ActivePlumbing PermitIrrigationSep 2026
View Details
2026-124522 PP
9405 FURMAN DR

Homebuilders loop for New SFR ref 2026-089182 BP. Austin Full purpose

FinalElectrical PermitHomebuilder LoopSep 2026
View Details
2026-114829 EP
IES Residential, Inc.
9405 FURMAN DR

Balboa S415 C Right New - 1 Story SFR w/ 4 bedrooms 3 bathrooms attached 2 car garage covered entry porch and patio required parking: 2.

ActiveElectrical PermitNewSep 2026
View Details
2026-089182 EP
IES Residential, Inc.
9405 CORVALLIS DR

Construct new driveway approach of 17 FT and sidewalk of 32 LF

ActiveDriveway / SidewalksNewAug 2026
View Details
2026-067539 DS
9405 FURMAN DR

Balboa S415 C Right New - 1 Story SFR w/ 4 bedrooms 3 bathrooms attached 2 car garage covered entry porch and patio required parking: 2.

ActiveMechanical PermitNewAug 2026
View Details
2026-089182 MP
IES Residential Inc

Watch all construction in 78719 (Austin)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.