Creekside at 1942

220 FM 1942 Rd, Crosby, TX 77532, Crosby, TX, 77532
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023007274
$3.0M
Project Value
15,650
Square Feet
$190/sqft
Cost/SqFt
1 year
Duration
Registered:Dec 12, 2022
Start:Mar 1, 2023
Target:Mar 1, 2024
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

One apartment building consisting of 3 STORIES, 32 units in Crosby TX. Without amenities, fenced, and gated

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 12, 2022
Construction Start
March 1, 2023
Expected Completion
March 1, 2024