๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

2113400 SAISD Edison High School Bond 2020

701 Santa Monica St, San Antonio, TX 78212, San Antonio, TX, 78212
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023007908
$280K
Project Value
48,960
Square Feet
$6/sqft
Cost/SqFt
1y 3mo
Duration
Registered:Dec 19, 2022
Start:Feb 28, 2023
Target:Jun 4, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Temporary portables to be placed at the SW parking lot of the school property. Portables will house six classrooms. HVAC, electrical and technology work will be provided for the commodity of the tenants. Two landings and two ramps will be provided.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 19, 2022
Construction Start
February 28, 2023
Expected Completion
June 4, 2024