โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

ClearWater McAllen

1100 S. 10th St, Mcallen, TX 78501, Mcallen, TX, 78501
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023010464
$1.2M
Project Value
4,954
Square Feet
$242/sqft
Cost/SqFt
9 months
Duration
Registered:Jan 27, 2023
Start:Mar 1, 2023
Target:Nov 30, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

New car wash facility

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 27, 2023
Construction Start
March 1, 2023
Expected Completion
November 30, 2023