โœ…Inspection Complete๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

WB Ball Early Childhood Center - classrooms addition

812 Shannon Ave., Seguin, TX 78155, Seguin, TX, 78155
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023013476
$2.5M
Project Value
4,879
Square Feet
$512/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Mar 7, 2023
Start:May 1, 2023
Target:Jun 30, 2024
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Construction of four classrooms and support spaces additions to an existing early childhood center. The construction is a suspended slab, brick over metal stud exterior walls, and built-up roof system

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 7, 2023
Construction Start
May 1, 2023
Expected Completion
June 30, 2024

Quick Actions

TDLR ID: TABS2023013476

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
JOSE S,CEDILLO
RAS #1060