๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

2023 Franklin Bond - Location "E" - Concession Stand

2925 FM 46, Franklin, TX 77856, Franklin, TX, 77856
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023014886
$1.1M
Project Value
1,640
Square Feet
$675/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Mar 24, 2023
Start:May 15, 2023
Target:Jul 1, 2024
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Project consists of a new 1,640 sf concession / restroom building for Franklin ISD.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 24, 2023
Construction Start
May 15, 2023
Expected Completion
July 1, 2024

Quick Actions

TDLR ID: TABS2023014886

Registered Accessibility Specialist

๐Ÿ“‹
JEFFERY L,KELLEY
RAS #55
780 N WATTERS RD STE 150, ALLEN, TX 75013