Inspection Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Panther Creek Parkway
DNT through to Preston Road SH 289, Frisco, TX 75033, Frisco, TX, 75033
Final Inspection85%
๐Project Metrics
TDLR #TABS2023015183$1.1M
Project Value
20,000
Square Feet
$54/sqft
Cost/SqFt
1y 9mo
Duration
Registered:Mar 28, 2023
Start:Jun 15, 2023
Target:Mar 15, 2025
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
New road construction consisting of pedestrian ways, drainage, concrete pavement, sidewalks, pavement markings, signs, sanitary sewer, and illumination from the Dallas North Tollway running east/west to Preston Road SH 289.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 28, 2023
Review Complete
+1047dMarch 28, 2023
Inspection Complete
February 7, 2026
Construction Start
June 15, 2023
Expected Completion
March 15, 2025
๐Related Projects
Property Owner
๐ค
CITY OF FRISCO ENGINEERING DEPARTMENT
Contact: Tin Nguyen
View company profile
6101 Frisco Square Blvd,3rd Fl, Frisco, Texas 75034
Design Firm
๐๏ธ
Kimley-Horn and Associates Inc
4 projects ยท $8.0M
View company profile
2201 W Royal Lane, Irving, Texas 75063