Project intelligenceTDLR TABS2023015807New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Jr High/High School Building Phase 2 - Veribest ISD

10062 FM Hwy 380, Veribest, TX, 76886

Construction complete · Mar 2026Project Closed

Jr High/High School Building Phase 2 - Veribest ISD is a new construction project at 10062 FM Hwy 380, Veribest, in Tom Green County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Mar 2026). The project has an estimated value of $9.2M across about 18,783 sq ft.

Estimated project value
$9.2M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
18,783 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$490/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 6mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Apr 5, 20231,080 days across supplied datesMar 20, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    453 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    548 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  5. Project closed · TDLR filing

    The project record was closed in TDLR.

    79 days after the preceding date shown.

    Source: TDLR filing

    View source record

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 76886 (Veribest)

One email per change. Unsubscribe in one click. Privacy.

Jr High/High School Building Phase 2 - Veribest ISD is a New Construction project located at 10062 FM Hwy 380, Veribest, TX 76886 in Veribest, Texas. The project has an estimated value of $9.2M covering 18,783 sq ft. Veribest ISD is the property owner and CADCO Architects and Engineers is the design firm of record. The project was registered with TDLR on April 5, 2023.

Frequently Asked Questions

What is Jr High/High School Building Phase 2 - Veribest ISD?

Jr High/High School Building Phase 2 - Veribest ISD is a new construction project at 10062 FM Hwy 380 in Veribest, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New Jr High/High School with Parking and Site Work

Is Jr High/High School Building Phase 2 - Veribest ISD open in Veribest?

Construction on Jr High/High School Building Phase 2 - Veribest ISD is complete — TDLR records show the project passed its required accessibility inspection in Mar 2026. The building is finished and very likely open.

Where is Jr High/High School Building Phase 2 - Veribest ISD located?

Jr High/High School Building Phase 2 - Veribest ISD is located at 10062 FM Hwy 380, Veribest, TX, 76886, in Tom Green County.

Who is the owner or developer of Jr High/High School Building Phase 2 - Veribest ISD?

Veribest ISD is the property owner/developer of record for Jr High/High School Building Phase 2 - Veribest ISD, per its TDLR project registration.

Who is the architect or design firm for Jr High/High School Building Phase 2 - Veribest ISD?

CADCO Architects and Engineers is the design firm of record for Jr High/High School Building Phase 2 - Veribest ISD, according to its TDLR filing.

How much does Jr High/High School Building Phase 2 - Veribest ISD cost and how big is it?

Jr High/High School Building Phase 2 - Veribest ISD has an estimated construction value of $9.2M and approximately 18,783 square feet (about $490/sqft), based on its TDLR filing.

Scope of Work

New Jr High/High School with Parking and Site Work

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

10062 FM Hwy 380, Veribest, TX, 76886

Location by street address

Watch all construction in 76886 (Veribest)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Veribest?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.