๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Sidewalk - Holland Avenue from Clinton Dr. to 18th St.
Holland Avenue from Clinton Dr. to 18th St., Houston, TX 77547, Houston, TX, 77547
Completed100%
๐Project Metrics
TDLR #TABS2023016158$875K
Project Value
27,180
Square Feet
$32/sqft
Cost/SqFt
5 months
Duration
Registered:Apr 10, 2023
Start:Nov 14, 2023
Target:Apr 14, 2024
๐
Project Closed
Project has been completed and closed
๐Scope of Work
The project consists of the construction of new sidewalks for Holland Avenue from Clinton Dr. to 18th St. along with relocation of utilities, sighs, reconstruction of driveways, sidewalk ramps, curb and gutter, pavement markings, and development of s
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 10, 2023
Construction Start
November 14, 2023
Expected Completion
April 14, 2024
๐Related Projects
๐คSame Owner
$1.3M totalProperty Owner
๐ค
Harris County Engineering Department
Contact: Luis Berrios
4 projects ยท $1.3M
View company profile
1111 Fannin St, 11th Floor, Houston, Texas 77002
Design Firm
๐๏ธ
AKV CONSULTING ENGINEERS
4 projects ยท $8.4M
View company profile
4600 Highway 6 North Suite 210, Houston, Texas 77084