โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Ingram High School New Band Hall

644 Hwy 39, Ingram, TX 78025, Ingram, TX, 78025
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023016511
$2.6M
Project Value
7,000
Square Feet
$371/sqft
Cost/SqFt
5 months
Duration
Registered:Apr 13, 2023
Start:Apr 17, 2023
Target:Sep 15, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

The construction of a new 7,000 square feet Band Hall with practice rooms, instrument and uniform storage, ensemble rooms, office, restrooms, and auxiliary spaces.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 13, 2023
Inspection Complete
September 15, 2023
Construction Start
April 17, 2023
Expected Completion
September 15, 2023

๐Ÿ“Location & Views

Open in MapsGet Directions|30.07132, -99.25935

Get alerts for Kerr

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists