Inspection Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Murphy USA Mineola
131 NE Loop 564, Mineola, TX 75773, Mineola, TX, 75773
Final Inspection85%
๐Project Metrics
TDLR #TABS2024000650$800K
Project Value
1,400
Square Feet
$571/sqft
Cost/SqFt
3 months
Duration
Registered:Sep 12, 2023
Start:Feb 5, 2024
Target:May 5, 2024
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Demo of existing Murphy and rebuild with new building, tanks,and canopy.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 12, 2023
Construction Start
February 5, 2024
Expected Completion
May 5, 2024