🏁Project Closed🔧 Additions to Existing Building💵 This project involves public funds, public land, or is a Federally funded roadway project.

SAN PERLITA FIRE STATION ADDITION

14115 FM 2209, San Perlita, TX 78580, San Perlita, TX, 78580
Completed100%

📊Project Metrics

TDLR #TABS2024001301
$280K
Project Value
1,518
Square Feet
$184/sqft
Cost/SqFt
4 months
Duration
Registered:Sep 19, 2023
Start:Nov 15, 2023
Target:Mar 14, 2024
🏁

Project Closed

Project has been completed and closed

📋Scope of Work

ADDITION OF 1518 SQ. FT., TO THE FIRE STATION, AS WELL AS, A PARKING LOT, IMPROVED DRAINAGE SYSTEM, CONCRETE SIDEWALK, AND UTILITY PAD, INSTALLATION OF POWER GENERATOR, AND ASPHALT ROAD TO ACCESS THE EXISTING FIRE STATION IN.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
September 19, 2023
Construction Start
November 15, 2023
Expected Completion
March 14, 2024