๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Cyrusne DFW4 | Shell & Upfit
Chelsea Blvd., Allen, TX 75013, Allen, TX, 75013
Construction50%
๐Project Metrics
TDLR #TABS2024002257$31.5M
Project Value
126,005
Square Feet
$250/sqft
Cost/SqFt
8 months
Duration
Registered:Oct 3, 2023
Start:Jan 2, 2024
Target:Sep 1, 2024
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New Construction, single-story Data Center with two-story office component. Total SF expected to be 126,005. Exterior construction to be insulated precast with steel structure.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 3, 2023
Construction Start
January 2, 2024
Expected Completion
September 1, 2024
๐Related Projects
๐คSame Owner
$1.31B totalProperty Owner
๐ค
CyrusOne
Contact: Tyler Powell
4 projects ยท $1.31B
View all projects
2850 N Harwood St., Dallas, Texas 75201
Design Firm
๐๏ธ
JHET Architects
4 projects ยท $486.5M
View all projects
3540 E Broad St. Ste 120-333, Mansfield, Texas 76063