๐Project Metrics
TDLR #TABS2024003388$7.5M
Project Value
200,000
Square Feet
$38/sqft
Cost/SqFt
1y 7mo
Duration
Registered:Oct 18, 2023
Start:Jan 8, 2024
Target:Jul 31, 2025
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Alteration of existing public right of way. Includes streets, curb ramps, and crosswalks at intersections and ramps and a roundabout at the intersection of Virginia St & Throckmorton St. (200,000 SF)
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 18, 2023
Review Complete
+828dOctober 18, 2023
Inspection Complete
January 23, 2026
Construction Start
January 8, 2024
Expected Completion
July 31, 2025
๐Related Projects
๐คSame Owner
$30.9M totalProperty Owner
๐ค
City of McKinney / CIP Manager
Contact: Aniswarie Kanamazina
4 projects ยท $30.9M
View company profile
221 N. Tennessee Street, McKinney, Texas 75069
Design Firm
๐๏ธ
Johnson, Mirmiran & Thompson (El Paso)
4 projects ยท $78.1M
View company profile
1575 Heritage Drive, Suite 308, McKinney, Texas 75069