๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Flatonia ISD Commons Lobby

400 E 4th St., Flatonia, TX 78941, Flatonia, TX, 78941
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024004428
$1.5M
Project Value
3,900
Square Feet
$385/sqft
Cost/SqFt
10 months
Duration
Registered:Oct 31, 2023
Start:Nov 1, 2023
Target:Sep 6, 2024
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Entryway addition to existing gym

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 31, 2023
Construction Start
November 1, 2023
Expected Completion
September 6, 2024