Grand Prairie Main Street Roundabout

E Main St. (SH 180), Grand Prairie, TX 75051, Grand Prairie, TX, 75051
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024004827
$260K
Project Value
575,000
Square Feet
$0/sqft
Cost/SqFt
3y 4mo
Duration
Registered:Nov 6, 2023
Start:May 6, 2024
Target:Aug 5, 2027
Remaining:586 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

For the construction of Jefferson Street intersection improvements; Construct roundabout consisting of: intersection improvements, shared use paths, sidewalks, landscaping, and pedestrian lighting

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 6, 2023
Construction Start
May 6, 2024
Expected Completion
August 5, 2027

๐Ÿ“Location & Views

Open in MapsGet Directions|32.74960, -96.92939

Quick Actions

TDLR ID: TABS2024004827