๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

TIRZ 13 - Sawyer Street & Edwards Street Multimodal Improvements

TIRZ 13 - Sawyer Street & Edwards Street, Houston, TX 77007, Houston, TX, 77007
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024005366
$702K
Project Value
10,000
Square Feet
$70/sqft
Cost/SqFt
5 months
Duration
Registered:Nov 14, 2023
Start:Jan 1, 2024
Target:May 30, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Multimodal signing and striping on Sawyer Street and Edwards Street. Provided 10' wide multi-use concrete sidewalk on Sawyer Street. 14" bike lane curbs, raised crosswalks and wheelchair ramp improvements.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 14, 2023
Construction Start
January 1, 2024
Expected Completion
May 30, 2024