๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Lamar CISD Transportation Center #3

4335 Highway 36 South, Rosenberg, TX 78539, Rosenberg, TX, 78539
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024006236
$21.6M
Project Value
30,000
Square Feet
$720/sqft
Cost/SqFt
1y 3mo
Duration
Registered:Nov 29, 2023
Start:Jan 1, 2024
Target:Apr 1, 2025
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Project consists of an administrative and bus facility to accommodate three school tracks.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 29, 2023
Construction Start
January 1, 2024
Expected Completion
April 1, 2025