Project intelligenceTDLR TABS2024006681New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Grand Prairie Fire Station 11

11005 Davis Dr, Midlothian, TX, 76065

Construction complete · Sep 2026Project Closed

Grand Prairie Fire Station 11 is a new construction project at 11005 Davis Dr, Midlothian, in Ellis County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Sep 2026). The project has an estimated value of $7.2M across about 10,714 sq ft.

Estimated project value
$7.2M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
10,714 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$672/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 4mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Dec 5, 20231,010 days across supplied datesSep 10, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    58 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    487 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  5. Project closed · TDLR filing

    The project record was closed in TDLR.

    465 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Grand Prairie Fire Station 11

Grand Prairie Fire Station 11 is a new construction project located at 11005 Davis Dr, Midlothian, TX 76065. The building spans 10,714 sq ft and was developed by the City of Grand Prairie. The estimated cost for this facility was $7,200,000, which calculates to $672 per square foot. The scope of work included the new fire station and associated sitework.

The project registered with TDLR in December 2023. Construction began in February 2024, and the filing indicated a scheduled completion date of June 2025. The final inspection passed in June 2025. TDLR closed the project file in September 2026, which marks the end of the accessibility review process for this construction. The status of the project is now Project Closed.

Financial Context

This investment is significant within Ellis County. Among 924 TDLR-registered new construction filings in the county, the median estimated cost is $900,000. The $7,200,000 cost for Fire Station 11 places it in the top quarter of projects by value. The median size for these filings is 7,476 sq ft, while this station is larger at 10,714 sq ft. The median cost per square foot in the county is $148, whereas this project averages $672 per square foot.

The City of Grand Prairie has other TDLR-registered projects, including the City Hall at $14,100,000 and Grand Prairie Fire Station 6 at $1,000,000. Both of those projects are closed. This station is part of a broader municipal infrastructure effort in the area. The funding involves public funds and public land.

Local Area Details

The project is situated in Midlothian, within Ellis County. Census estimates for ZIP code 76065 show a population of about 44,614. The median household income is $123,664, and the median owner-occupied home value is $378,600. The area has 15,081 housing units. Other nearby registered projects include the 220 N. Mitchell Road Office Building and the NexaDose Pharmacy.

The construction window for this project was 487 days, which is longer than the county median of 244 days. The Ellis County unemployment rate was 4.5 percent in July 2026. The project is complete, with the file closed by TDLR.

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 76065 (Midlothian)

One email per change. Unsubscribe in one click. Privacy.

Grand Prairie Fire Station 11 is a New Construction project located at 11005 Davis Dr, Midlothian, TX 76065 in Midlothian, Texas. The project has an estimated value of $7.2M covering 10,714 sq ft. CITY OF GRAND PRAIRIE is the property owner. The project was registered with TDLR on December 5, 2023.

Frequently Asked Questions

Is Grand Prairie Fire Station 11 open?

The TDLR record shows the construction is complete and the file is closed. The record does not state when the station opened for public business or daily operations.

Where is the new fire station located?

The address is 11005 Davis Dr, Midlothian, TX 76065. It is in Ellis County, Texas.

How much did the project cost?

The estimated cost was $7,200,000. This works out to $672 per square foot for the 10,714 sq ft building.

Who owns the building?

The owner of record is the City of Grand Prairie. The project involved public funds and public land.

When was the construction finished?

The final inspection passed in June 2025. TDLR closed the project file in September 2026.

What is Grand Prairie Fire Station 11?

Grand Prairie Fire Station 11 is a new construction project at 11005 Davis Dr in Midlothian, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: new fire station and associated sitework

Is Grand Prairie Fire Station 11 open in Midlothian?

Construction on Grand Prairie Fire Station 11 is complete — TDLR records show the project passed its required accessibility inspection in Sep 2026. The building is finished and very likely open.

Where is Grand Prairie Fire Station 11 located?

Grand Prairie Fire Station 11 is located at 11005 Davis Dr, Midlothian, TX, 76065, in Ellis County.

Who is the owner or developer of Grand Prairie Fire Station 11?

CITY OF GRAND PRAIRIE is the property owner/developer of record for Grand Prairie Fire Station 11, per its TDLR project registration.

How much does Grand Prairie Fire Station 11 cost and how big is it?

Grand Prairie Fire Station 11 has an estimated construction value of $7.2M and approximately 10,714 square feet (about $672/sqft), based on its TDLR filing.

Scope of Work

new fire station and associated sitework

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

11005 Davis Dr, Midlothian, TX, 76065

Location by street address

Watch all construction in 76065 (Midlothian)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Midlothian?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.