Project intelligenceTDLR TABS2024006955Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Building "C" 2023 Bond Intermediate & Elementary School Additions

12800 State Hwy 64, Tyler, TX, 75707

Construction complete · May 2026Project Closed

Building "C" 2023 Bond Intermediate & Elementary School Additions is a renovation/alteration project at 12800 State Hwy 64, Tyler, in Smith County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed May 2026). The project has an estimated value of $2.4M across about 9,015 sq ft.

Estimated project value
$2.4M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
9,015 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$266/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
16 days
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Dec 8, 2023875 days across supplied datesMay 1, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    66 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    16 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  5. Project closed · TDLR filing

    The project record was closed in TDLR.

    793 days after the preceding date shown.

    Source: TDLR filing

    View source record

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75707 (Tyler)

One email per change. Unsubscribe in one click. Privacy.

Building "C" 2023 Bond Intermediate & Elementary School Additions is a Renovation/Alteration project located at 12800 State Hwy 64, Tyler, TX 75707 in Tyler, Texas. The project has an estimated value of $2.4M covering 9,015 sq ft. Chapel Hill Independent School District is the property owner and Harris Craig Architects, Inc. is the design firm of record. The project was registered with TDLR on December 8, 2023.

Frequently Asked Questions

What is Building "C" 2023 Bond Intermediate & Elementary School Additions?

Building "C" 2023 Bond Intermediate & Elementary School Additions is a renovation/alteration project at 12800 State Hwy 64 in Tyler, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Project includes approximately 9,015 SF level 2 alterations and cosmetic upgrades at Kissam Intermediate School.

Is Building "C" 2023 Bond Intermediate & Elementary School Additions open in Tyler?

Construction on Building "C" 2023 Bond Intermediate & Elementary School Additions is complete — TDLR records show the project passed its required accessibility inspection in May 2026. The building is finished and very likely open.

Where is Building "C" 2023 Bond Intermediate & Elementary School Additions located?

Building "C" 2023 Bond Intermediate & Elementary School Additions is located at 12800 State Hwy 64, Tyler, TX, 75707, in Smith County.

Who is the owner or developer of Building "C" 2023 Bond Intermediate & Elementary School Additions?

Chapel Hill Independent School District is the property owner/developer of record for Building "C" 2023 Bond Intermediate & Elementary School Additions, per its TDLR project registration.

Who is the architect or design firm for Building "C" 2023 Bond Intermediate & Elementary School Additions?

Harris Craig Architects, Inc. is the design firm of record for Building "C" 2023 Bond Intermediate & Elementary School Additions, according to its TDLR filing.

How much does Building "C" 2023 Bond Intermediate & Elementary School Additions cost and how big is it?

Building "C" 2023 Bond Intermediate & Elementary School Additions has an estimated construction value of $2.4M and approximately 9,015 square feet (about $266/sqft), based on its TDLR filing.

Scope of Work

Project includes approximately 9,015 SF level 2 alterations and cosmetic upgrades at Kissam Intermediate School.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

12800 State Hwy 64, Tyler, TX, 75707

Location by street address

Watch all construction in 75707 (Tyler)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.