Inspection Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
2023 Bond Project New Parking Lot At Pampa High School
111 E. Harvester, Pampa, TX 79065, Pampa, TX, 79065
Final Inspection85%
๐Project Metrics
TDLR #TABS2024012158$800K
Project Value
44,000
Square Feet
$18/sqft
Cost/SqFt
4 months
Duration
Registered:Feb 22, 2024
Start:Apr 15, 2024
Target:Aug 23, 2024
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Construct New Parking Lot
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 22, 2024
Construction Start
April 15, 2024
Expected Completion
August 23, 2024
Property Owner
๐ค
PAMPA I S D
Contact: Hugh Piatt II, Superintendent
View company profile
1233 N. Hobart, Pampa, Texas 79065
Design Firm
๐๏ธ
Shiver Megert & Associates, LLP
4 projects ยท $24.5M
View company profile
102 S.E. 9th Ave, Amarillo, Texas 79101