๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Hwy 287 & 156

10021 US-287, Fort Worth, TX 76131, Fort Worth, TX, 76131
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024012824
$250K
Project Value
2,224
Square Feet
$112/sqft
Cost/SqFt
3 months
Duration
Registered:Mar 1, 2024
Start:Aug 2, 2024
Target:Oct 21, 2024
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Renovation of existing Starbucks cafe including minor wall framing, casework, finishes, electrical, & MEP work. 2,224sf

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 1, 2024
Construction Start
August 2, 2024
Expected Completion
October 21, 2024