Project intelligenceTDLR TABS2024013412Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

SEMINOLE ISD 2023 BOND CTE Center

2100 NW Avenue D, Seminole, TX, 79360

Target date passed (Aug 2026)Review Complete

SEMINOLE ISD 2023 BOND CTE Center is a renovation/alteration project at 2100 NW Avenue D, Seminole, in Gaines County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Aug 2026 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $25.0M across about 64,222 sq ft.

Estimated project value
$25.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
64,222 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$389/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
2y 5mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Mar 8, 2024903 days across supplied datesAug 28, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    38 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    865 days after the preceding date shown.

    Source: TDLR filing

    View source record

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 79360 (Seminole)

One email per change. Unsubscribe in one click. Privacy.

SEMINOLE ISD 2023 BOND CTE Center is a Renovation/Alteration project located at 2100 NW Avenue D, Seminole, TX 79360 in Seminole, Texas. The project has an estimated value of $25.0M covering 64,222 sq ft. SEMINOLE ISD is the property owner and PARKHILL is the design firm of record. The project was registered with TDLR on March 8, 2024.

Frequently Asked Questions

What is SEMINOLE ISD 2023 BOND CTE Center?

SEMINOLE ISD 2023 BOND CTE Center is a renovation/alteration project at 2100 NW Avenue D in Seminole, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: CTE Center Addition & Renovation - 47,017 sq ft and addition of 17,205 sq ft to include vertical building construction, site work, landscaping, paving, and site utilities.

Is SEMINOLE ISD 2023 BOND CTE Center open in Seminole?

SEMINOLE ISD 2023 BOND CTE Center was scheduled to finish construction in Aug 2026 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is SEMINOLE ISD 2023 BOND CTE Center located?

SEMINOLE ISD 2023 BOND CTE Center is located at 2100 NW Avenue D, Seminole, TX, 79360, in Gaines County.

Who is the owner or developer of SEMINOLE ISD 2023 BOND CTE Center?

SEMINOLE ISD is the property owner/developer of record for SEMINOLE ISD 2023 BOND CTE Center, per its TDLR project registration.

Who is the architect or design firm for SEMINOLE ISD 2023 BOND CTE Center?

PARKHILL is the design firm of record for SEMINOLE ISD 2023 BOND CTE Center, according to its TDLR filing.

How much does SEMINOLE ISD 2023 BOND CTE Center cost and how big is it?

SEMINOLE ISD 2023 BOND CTE Center has an estimated construction value of $25.0M and approximately 64,222 square feet (about $389/sqft), based on its TDLR filing.

Scope of Work

CTE Center Addition & Renovation - 47,017 sq ft and addition of 17,205 sq ft to include vertical building construction, site work, landscaping, paving, and site utilities.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

2100 NW Avenue D, Seminole, TX, 79360

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 79360 (Seminole)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Seminole?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.