Project intelligenceTDLR TABS2024016362Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

High School Band Tower

5201 Ross Rd., Del Valle, TX, 78617

Construction complete · Jul 2024Project Closed

High School Band Tower is a renovation/alteration project at 5201 Ross Rd., Del Valle, in Travis County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jul 2024). The project has an estimated value of $370K across about 100,000 sq ft.

Estimated project value
$370K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
100,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$4/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
2 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Apr 17, 2024105 days across supplied datesJul 31, 2024

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    45 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Project closed · TDLR filing

    The project record was closed in TDLR.

    60 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78617 (Del Valle)

One email per change. Unsubscribe in one click. Privacy.

High School Band Tower is a Renovation/Alteration project located at 5201 Ross Rd., Del Valle, TX 78617 in Del Valle, Texas. The project has an estimated value of $370K covering 100,000 sq ft. Del Valle Independent School District is the property owner and Pfluger Architects is the design firm of record. The project was registered with TDLR on April 17, 2024.

Frequently Asked Questions

What is High School Band Tower?

High School Band Tower is a renovation/alteration project at 5201 Ross Rd. in Del Valle, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Addition of Band Tower in band practice parking area with re-stripping.

Is High School Band Tower open in Del Valle?

Construction on High School Band Tower is complete — TDLR records show the project passed its required accessibility inspection in Jul 2024. The building is finished and very likely open.

Where is High School Band Tower located?

High School Band Tower is located at 5201 Ross Rd., Del Valle, TX, 78617, in Travis County.

Who is the owner or developer of High School Band Tower?

Del Valle Independent School District is the property owner/developer of record for High School Band Tower, per its TDLR project registration.

Who is the architect or design firm for High School Band Tower?

Pfluger Architects is the design firm of record for High School Band Tower, according to its TDLR filing.

How much does High School Band Tower cost and how big is it?

High School Band Tower has an estimated construction value of $370K and approximately 100,000 square feet (about $4/sqft), based on its TDLR filing.

Scope of Work

Addition of Band Tower in band practice parking area with re-stripping.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

5201 Ross Rd., Del Valle, TX, 78617

Location by street address

Related City Permits

Building permits found at or near this location

5201 BERKMAN DR

Installation of two (2) light posts for security lighting around the playground in the park. 2026-038815 DA.

ActiveElectrical PermitNewSep 2026
View Details
2026-088998 EP
Elk Electric, Inc.
5201 BERKMAN DR

Installation of two (2) light posts for security lighting around the playground in the park. 2026-038815 DA.

ActiveBuilding PermitNewSep 2026
$50K
View Details
2026-088998 BP
Austin Parks and Recreation
5201 EMERALD FOREST DR

Replacement of an existing water heater

FinalPlumbing PermitChange OutAug 2026
View Details
2026-104803 PP
Austin Select Plumbing
5201 BONNEVILLE BND

ETJ - 200amp panel replacement *Has AE- Disconnect and Reconnect only*

FinalElectrical PermitRepairJun 2026
View Details
2026-071900 EP
Mister Sparky Austin
5201 EILERS AVE

Temporary power to home approved ESPA form will be attached. Ref: 2026-029559-BP

FinalElectrical PermitHomebuilder LoopMay 2026
View Details
2026-058788 EP
Pritchard Electric

Watch all construction in 78617 (Del Valle)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Del Valle?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.