โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

FM 1960 (CSJ: 1685-01-107)

From: Mills Rd To: SH 249, Houston, TX 77070, Houston, TX, 77070
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024016588
$283K
Project Value
41,007
Square Feet
$7/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Apr 19, 2024
Start:Jul 26, 2023
Target:Mar 26, 2025
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Construct shared use path, sidewalk, curb ramps, drainage modifications, signal modifications and signing.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 19, 2024
Construction Start
July 26, 2023
Expected Completion
March 26, 2025