CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION

302 W. 10th Street, Crane, TX, 79731

Construction complete · Aug 2026Inspection Complete

CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION is a renovation/alteration project at 302 W. 10th Street, Crane, in Crane County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Aug 2026). The project has an estimated value of $41.8M across about 65,000 sq ft.

Estimated project value
$41.8M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
65,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$642/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
2y 2mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Apr 26, 2024830 days across supplied datesAug 4, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    32 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    790 days after the preceding date shown.

    Source: TDLR filing

    View source record
  5. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    8 days after the preceding date shown.

    Source: TDLR filing

    View source record

Inspection Complete

Final inspection completed, awaiting project closure

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 79731 (Crane)

One email per change. Unsubscribe in one click. Privacy.

CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION is a Renovation/Alteration project located at 302 W. 10th Street, Crane, TX 79731 in Crane, Texas. The project has an estimated value of $41.8M covering 65,000 sq ft. Crane ISD is the property owner and PARKHILL is the design firm of record. The project was registered with TDLR on April 26, 2024.

Frequently Asked Questions

What is CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION?

CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION is a renovation/alteration project at 302 W. 10th Street in Crane, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New construction and renovation to the existing facility. The new, single story, Middle School will consist of an education and administration wing located on the west side, along with a new gym on the east side. 55,000 new and 10,000 re…

Is CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION open in Crane?

Construction on CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION is complete — TDLR records show the project passed its required accessibility inspection in Aug 2026. The building is finished and very likely open.

Where is CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION located?

CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION is located at 302 W. 10th Street, Crane, TX, 79731, in Crane County.

Who is the owner or developer of CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION?

Crane ISD is the property owner/developer of record for CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION, per its TDLR project registration.

Who is the architect or design firm for CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION?

PARKHILL is the design firm of record for CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION, according to its TDLR filing.

How much does CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION cost and how big is it?

CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION has an estimated construction value of $41.8M and approximately 65,000 square feet (about $642/sqft), based on its TDLR filing.

Scope of Work

New construction and renovation to the existing facility. The new, single story, Middle School will consist of an education and administration wing located on the west side, along with a new gym on the east side. 55,000 new and 10,000 reno sf

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

302 W. 10th Street, Crane, TX, 79731

Location by street address

Watch all construction in 79731 (Crane)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.