Project Gateway - North Office Tower

301 Sheehy Pkwy, Waco, TX 76712, Waco, TX, 76712
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024017538
$8.0M
Project Value
18,500
Square Feet
$432/sqft
Cost/SqFt
1y 7mo
Duration
Registered:May 2, 2024
Start:Jan 2, 2024
Target:Aug 1, 2025
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

New 18,500 sq.ft. administrative tower attached to new paper processing mill.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 2, 2024
Construction Start
January 2, 2024
Expected Completion
August 1, 2025