Chisholm Trail South Improvements (Old Town)
Chisholm Trail Rd, Round Rock, TX 78681, Round Rock, TX, 78681
Construction50%
๐Project Metrics
TDLR #TABS2024018694$5.0M
Project Value
73,710
Square Feet
$68/sqft
Cost/SqFt
1y 7mo
Duration
Registered:May 16, 2024
Start:Jan 10, 2025
Target:Jul 29, 2026
Remaining:212 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
The project will reconstruct about 73,710 square feet (1.69 acres) of facilities on Chisholm Trail Rd. Chisholm Trail will be reconstructed from Sam Bass Rd to RM 620, including pavement, curb & gutter, sidewalk, storm sewer, and illumination.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 16, 2024
Construction Start
January 10, 2025
Expected Completion
July 29, 2026
๐Related Projects
๐คSame Owner
$53.7M totalProperty Owner
๐ค
City of Round Rock
Contact: Dawn Scheel
4 projects ยท $53.7M
View all projects
3400 Sunrise Road, Round Rock, Texas 78665
Design Firm
๐๏ธ
Freese and Nichols, Inc.
4 projects ยท $23.5M
View company profile
10431 Morado Cir Suite 300, Austin, Texas 78727