Project intelligenceTDLR TABS2024019389New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Traffic Signal Improvements (0915-00-260) in San Antonio, TX

Various Locations, San Antonio, TX, 78229

Construction complete · Mar 2026Inspection Complete

Traffic Signal Improvements (0915-00-260) is a new construction project at Various Locations, San Antonio, in Bexar County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Mar 2026). The project has an estimated value of $104K across about 2,335 sq ft.

Estimated project value
$104K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
2,335 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$45/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 3mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

May 27, 2024668 days across supplied datesMar 26, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    128 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    456 days after the preceding date shown.

    Source: TDLR filing

    View source record
  5. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    84 days after the preceding date shown.

    Source: TDLR filing

    View source record

Inspection Complete

Final inspection completed, awaiting project closure

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78229 (San Antonio)

One email per change. Unsubscribe in one click. Privacy.

Traffic Signal Improvements (0915-00-260) is a New Construction project located at Various Locations, San Antonio, TX 78229 in San Antonio, Texas. The project has an estimated value of $104K covering 2,335 sq ft. TxDOT District: San Antonio is the property owner. The project was registered with TDLR on May 27, 2024.

Frequently Asked Questions

What is Traffic Signal Improvements (0915-00-260)?

Traffic Signal Improvements (0915-00-260) is a new construction project at Various Locations in San Antonio, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: District wide Non-Site specific Traffic Signals FY 2024 Project 2

Is Traffic Signal Improvements (0915-00-260) open in San Antonio?

Construction on Traffic Signal Improvements (0915-00-260) is complete — TDLR records show the project passed its required accessibility inspection in Mar 2026. The building is finished and very likely open.

Where is Traffic Signal Improvements (0915-00-260) located?

Traffic Signal Improvements (0915-00-260) is located at Various Locations, San Antonio, TX, 78229, in Bexar County.

Who is the owner or developer of Traffic Signal Improvements (0915-00-260)?

TxDOT District: San Antonio is the property owner/developer of record for Traffic Signal Improvements (0915-00-260), per its TDLR project registration.

How much does Traffic Signal Improvements (0915-00-260) cost and how big is it?

Traffic Signal Improvements (0915-00-260) has an estimated construction value of $104K and approximately 2,335 square feet (about $45/sqft), based on its TDLR filing.

Scope of Work

District wide Non-Site specific Traffic Signals FY 2024 Project 2

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Various Locations, San Antonio, TX, 78229

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 78229 (San Antonio)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in San Antonio?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.