Sidewalk - N. Eldridge Pkwy

0 N Eldridge Pkwy, Houston, TX 77041, Houston, TX, 77041
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024021157
$1.6M
Project Value
40,000
Square Feet
$41/sqft
Cost/SqFt
3 months
Duration
Registered:Jun 19, 2024
Start:Aug 25, 2024
Target:Nov 25, 2024
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Design and construction of a 5' wide concrete sidewalk to include wheelchair ramps at all public street intersections, properly sloped driveways and regarding/curb treatments where steep grades require it.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 19, 2024
Construction Start
August 25, 2024
Expected Completion
November 25, 2024