๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

TOM TAYLOR REGIONAL WATER TREATMENT PLANT

900 N KEALY ST, Lewisville, TX 75057, Lewisville, TX, 75057
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024025226
$2.0M
Project Value
3,000
Square Feet
$667/sqft
Cost/SqFt
2y 7mo
Duration
Registered:Aug 12, 2024
Start:Jan 20, 2025
Target:Jul 30, 2027
Remaining:581 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

NEW CONSTRUCTION

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 12, 2024
Construction Start
January 20, 2025
Expected Completion
July 30, 2027