Construction complete ยท Feb 2026โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

North Smythe Street Sidewalk Reconstruction

100 N Smythe St, Bowie, TX 76230, Bowie, TX, 76230

North Smythe Street Sidewalk Reconstruction is a renovation/alteration project at 100 N Smythe St, Bowie, in Montague County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Feb 2026). The project has an estimated value of $455K across about 9,754 sq ft.

Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025005603
$455K
Project Value
9,754
Square Feet
$47/sqft
Cost/SqFt
5 months
Duration
Registered:Nov 14, 2024
Start:Feb 5, 2025
Target:Jul 5, 2025
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

North Smythe Street Sidewalk Reconstruction is a Renovation/Alteration project located at 100 N Smythe St, Bowie, TX 76230 in Bowie, Texas. The project has an estimated value of $455K covering 9,754 sq ft. City of Bowie is the property owner and Hayter Engineering is the design firm of record. The project was registered with TDLR on November 14, 2024.

โ“Frequently Asked Questions

What is North Smythe Street Sidewalk Reconstruction?

North Smythe Street Sidewalk Reconstruction is a renovation/alteration project at 100 N Smythe St in Bowie, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: 3,438 square feet of sidewalk reconstruction, 4,023 square feet of brick street repair, 549 square feet of concrete parking, 882 square feet of new concrete street, 295 linear feet of new curb & gutter, 567 square feet of new concrete drโ€ฆ

Is North Smythe Street Sidewalk Reconstruction open in Bowie?

Construction on North Smythe Street Sidewalk Reconstruction is complete โ€” TDLR records show the project passed its required accessibility inspection in Feb 2026. The building is finished and very likely open.

Where is North Smythe Street Sidewalk Reconstruction located?

North Smythe Street Sidewalk Reconstruction is located at 100 N Smythe St, Bowie, TX, 76230, in Montague County.

Who is the owner or developer of North Smythe Street Sidewalk Reconstruction?

City of Bowie is the property owner/developer of record for North Smythe Street Sidewalk Reconstruction, per its TDLR project registration.

Who is the architect or design firm for North Smythe Street Sidewalk Reconstruction?

Hayter Engineering is the design firm of record for North Smythe Street Sidewalk Reconstruction, according to its TDLR filing.

How much does North Smythe Street Sidewalk Reconstruction cost and how big is it?

North Smythe Street Sidewalk Reconstruction has an estimated construction value of $455K and approximately 9,754 square feet (about $47/sqft), based on its TDLR filing.

๐Ÿ“‹Scope of Work

3,438 square feet of sidewalk reconstruction, 4,023 square feet of brick street repair, 549 square feet of concrete parking, 882 square feet of new concrete street, 295 linear feet of new curb & gutter, 567 square feet of new concrete drive.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 14, 2024
Review Complete
+456d
November 14, 2024
Inspection Complete
February 13, 2026
Construction Start
February 5, 2025
Expected Completion
July 5, 2025

๐Ÿ“…Project Timeline

Filed

Nov 14, 2024

Review Complete

Nov 14, 2024

Inspection Complete

Feb 13, 2026

Closed

456d

Construction phase

Get alerts for Montague

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists