Inspection Complete๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Tool City Hall Addition
701 N. Tool Dr., Tool, TX 75143, Tool, TX, 75143
Final Inspection85%
๐Project Metrics
TDLR #TABS2025005657$750K
Project Value
3,600
Square Feet
$208/sqft
Cost/SqFt
6 months
Duration
Registered:Nov 15, 2024
Start:Sep 16, 2024
Target:Mar 1, 2025
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Approx. 3,600 sf of city hall offices, including lobby, breakroom, restroom, conference room
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 15, 2024
Construction Start
September 16, 2024
Expected Completion
March 1, 2025
๐Related Projects
๐คSame Owner
$2.6M totalProperty Owner
๐ค
CITY OF TOOL
Contact: Julius Kizzee
3 projects ยท $2.6M
View company profile
701 N. Tool Dr., Tool, Texas 75143
Design Firm
๐๏ธ
PAUL E CANUP ARCHITECT
View company profile
301 E. Will White Road, Tool, Texas 75143