Big Spring Field Office (BSFO) Expansion
98 N Midway Road, Big Spring, TX, 79720
Big Spring Field Office (BSFO) Expansion is a additions to existing building project at 98 N Midway Road, Big Spring, in Howard County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Mar 2025). The project has an estimated value of $2.2M across about 9,500 sq ft.
- Estimated project value
- $2.2M
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 9,500 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $229/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 4 months
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
4 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
21 days after the preceding date shown.
Source: TDLR filing
View source recordProject closed · TDLR filing
The project record was closed in TDLR.
112 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
Same day as the preceding date shown.
Source: TDLR filing
View source record
Project Closed
Project has been completed and closed
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 79720 (Big Spring)
One email per change. Unsubscribe in one click. Privacy.
Big Spring Field Office (BSFO) Expansion is a Additions to Existing Building project located at 98 N Midway Road, Big Spring, TX 79720 in Big Spring, Texas. The project has an estimated value of $2.2M covering 9,500 sq ft. Wind Energy Transmission Texas, LLC is the property owner. The project was registered with TDLR on November 18, 2024.
Frequently Asked Questions
What is Big Spring Field Office (BSFO) Expansion?
Big Spring Field Office (BSFO) Expansion is a additions to existing building project at 98 N Midway Road in Big Spring, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Expansion to the current Big Spring Field Office, as well as new additions to the Big Spring Field Office Shop and parking area. Estimated square footage si 9,500swft
Is Big Spring Field Office (BSFO) Expansion open in Big Spring?
Construction on Big Spring Field Office (BSFO) Expansion is complete — TDLR records show the project passed its required accessibility inspection in Mar 2025. The building is finished and very likely open.
Where is Big Spring Field Office (BSFO) Expansion located?
Big Spring Field Office (BSFO) Expansion is located at 98 N Midway Road, Big Spring, TX, 79720, in Howard County.
Who is the owner or developer of Big Spring Field Office (BSFO) Expansion?
Wind Energy Transmission Texas, LLC is the property owner/developer of record for Big Spring Field Office (BSFO) Expansion, per its TDLR project registration.
How much does Big Spring Field Office (BSFO) Expansion cost and how big is it?
Big Spring Field Office (BSFO) Expansion has an estimated construction value of $2.2M and approximately 9,500 square feet (about $229/sqft), based on its TDLR filing.
Scope of Work
Expansion to the current Big Spring Field Office, as well as new additions to the Big Spring Field Office Shop and parking area. Estimated square footage si 9,500swft
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
98 N Midway Road, Big Spring, TX, 79720
Related Projects
Watch all construction in 79720 (Big Spring)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Big Spring?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.