Funding type
This project involves public funds, public land, or is a Federally funded roadway project.
Rodman Street SUP PE/CONS in Horizon City, TX
Rodman DR from FM 1281(Horizon Blvd) to Veny Webb, Horizon City, TX, 79928
Rodman Street SUP PE/CONS is a new construction project at Rodman DR from FM 1281(Horizon Blvd) to Veny Webb, Horizon City, in El Paso County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Aug 2026). The project has an estimated value of $725K across about 10,000 sq ft.
- Estimated project value
- $725K
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 10,000 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $72/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 7 months
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
6 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordReview complete · TDLR filing
The filing records completion of the accessibility review.
Same day as the preceding date shown.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
194 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
199 days after the preceding date shown.
Source: TDLR filing
View source recordInspection complete · TDLR filing
The filing records completion of the accessibility inspection.
90 days after the preceding date shown.
Source: TDLR filing
View source recordProject closed · TDLR filing
The project record was closed in TDLR.
140 days after the preceding date shown.
Source: TDLR filing
View source record
📰About Rodman Street SUP PE/CONS
Rodman Street SUP PE/CONS is a completed new construction project in Horizon City, Texas. The work involved building a 10-foot-wide shared use path along Rodman Drive, stretching from FM 1281 (Horizon Blvd) to Veny Webb Street. The total estimated cost for this infrastructure upgrade was $724,744, covering a 10,000 sq ft area. The project is now fully finished, with TDLR closed the project file in August 2026.
The Town of Horizon City owned the project and hired Consor Engineers, LLC for design services. Julie Ericson Gereda served as the registered accessibility specialist. The scope of work included concrete header curb installation, path paving, driveway reconstruction, and signage. This construction used public funds and public land, qualifying it for specific federal and state oversight standards.
Project Timeline and Completion
The project registered with TDLR in November 2024, with plan review completing in the same month. Construction was scheduled to begin in June 2025. The filing listed a completion date of December 2025, which has passed. A final inspection passed in March 2026, confirming the work met required standards. This sequence confirms the project is no longer under active construction review.
Compared to 2,654 similar new construction filings in El Paso County, this project’s cost is close to the county median of $800,000. The scheduled build window of 199 days is close to the county median of 214 days. However, the cost per square foot of $72 is below the county median of $111. These figures indicate an efficient build relative to regional averages for similar accessibility infrastructure projects.
Local Context and Ownership
The Town of Horizon City has three other TDLR-registered projects, totaling $997,832. These include Park B and Park A in Horizon City, and a traffic signal design project in El Paso. Consor Engineers, LLC has worked on six other registered projects across Texas, with a combined value of $421,254,196. These range from small local improvements to major state highway projects in cities like Amarillo and Fort Worth.
Horizon City is located in El Paso County, with a ZIP code population of about 82,792 people. The median household income in this area is $73,704, and the median owner-occupied home value is $188,600. Housing in this region is predominantly owner-occupied. The unemployment rate in El Paso County was 4.6 percent in August 2026, lower than a year earlier. This economic context helps explain the steady demand for public infrastructure improvements in the area.
Project Closed
Project has been completed and closed
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 79928 (Horizon City)
One email per change. Unsubscribe in one click. Privacy.
Rodman Street SUP PE/CONS is a New Construction project located at Rodman DR from FM 1281(Horizon Blvd) to Veny Webb, Horizon City, TX 79928 in Horizon City, Texas. The project has an estimated value of $725K covering 10,000 sq ft. Town of Horizon City is the property owner and Consor Engineers, LLC is the design firm of record. The project was registered with TDLR on November 20, 2024.
Frequently Asked Questions
Is the Rodman Street shared use path open?
The TDLR record shows the project is closed, with a final inspection passed in March 2026. This indicates the construction is complete, but the record does not specify public access dates.
Who built the Rodman Street project?
Consor Engineers, LLC was the design firm of record. The Town of Horizon City is the owner. The filing does not list the general contractor by name.
How much did the project cost?
The estimated cost was $724,744. This covers a 10,000 sq ft area, resulting in a cost of $72 per square foot.
When did the project finish?
The final inspection passed in March 2026. TDLR closed the project file in August 2026, marking the end of the accessibility review process.
What was included in the scope of work?
The scope included a 10-foot-wide shared use path, concrete header curb, path paving, driveway reconstruction, and signage installation.
What is Rodman Street SUP PE/CONS?
Rodman Street SUP PE/CONS is a new construction project at Rodman DR from FM 1281(Horizon Blvd) to Veny Webb in Horizon City, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: construction of anew 10 foot wide shared use path with concrete header curb, path paving, reconstruction of driveways and signage
Is Rodman Street SUP PE/CONS open in Horizon City?
Construction on Rodman Street SUP PE/CONS is complete — TDLR records show the project passed its required accessibility inspection in Aug 2026. The building is finished and very likely open.
Where is Rodman Street SUP PE/CONS located?
Rodman Street SUP PE/CONS is located at Rodman DR from FM 1281(Horizon Blvd) to Veny Webb, Horizon City, TX, 79928, in El Paso County.
Who is the owner or developer of Rodman Street SUP PE/CONS?
Town of Horizon City is the property owner/developer of record for Rodman Street SUP PE/CONS, per its TDLR project registration.
Who is the architect or design firm for Rodman Street SUP PE/CONS?
Consor Engineers, LLC is the design firm of record for Rodman Street SUP PE/CONS, according to its TDLR filing.
How much does Rodman Street SUP PE/CONS cost and how big is it?
Rodman Street SUP PE/CONS has an estimated construction value of $725K and approximately 10,000 square feet (about $72/sqft), based on its TDLR filing.
Scope of Work
construction of anew 10 foot wide shared use path with concrete header curb, path paving, reconstruction of driveways and signage
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
Rodman DR from FM 1281(Horizon Blvd) to Veny Webb, Horizon City, TX, 79928
Explore the supplied address
A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.
Related Projects
Same Owner
$10.7M totalWatch all construction in 79928 (Horizon City)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Horizon City?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.