๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
US 90A (CSJ: 0027-08-147)
From: FM 359 To: SH 99, Richmond, TX 77406, Richmond, TX, 77406
Construction50%
๐Project Metrics
TDLR #TABS2025006653$62.2M
Project Value
138,616
Square Feet
$449/sqft
Cost/SqFt
2y 4mo
Duration
Registered:Dec 2, 2024
Start:Jul 1, 2025
Target:Nov 1, 2027
Remaining:674 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Reconstruct and widen from 4 to 6 lane divided roadway. Construct drainage cross culverts, storm sewer, detention pond and Shared Use Path (SUP).
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 2, 2024
Construction Start
July 1, 2025
Expected Completion
November 1, 2027
๐Related Projects
๐คSame Owner
$96.5M totalProperty Owner
๐ค
TxDOT District: Houston
Contact: Daniel Dvorak, P.E.
4 projects ยท $96.5M
View company profile
7600 Washington Avenue, Houston, Texas 77007
Design Firm
๐๏ธ
CONSOR ENGINEERING
4 projects ยท $118.8M
View company profile
15340 Park Row, Houston, Texas 77084