Project intelligenceTDLR TABS2025006858New Construction
Funding type

This project is privately funded, on private land for private use.

T-Project - Production in Taylor, TX

140 Logistics Loop East, Building 03, Taylor, TX, 76574

Construction complete · Feb 2026Project Closed

T-Project - Production is a new construction project at 140 Logistics Loop East, Building 03, Taylor, in Williamson County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Feb 2026). The project has an estimated value of $10.0M across about 35,492 sq ft.

Estimated project value
$10.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
35,492 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$282/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 7mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Dec 4, 2024670 days across supplied datesOct 5, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    89 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Project closed · TDLR filing

    The project record was closed in TDLR.

    361 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    220 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About T-Project - Production

T-Project - Production is a new 35,492 sq ft facility at 140 Logistics Loop East, Building 03, in Taylor, Texas. The project, valued at $10,000,000, represents a significant industrial addition to Williamson County, with a calculated cost of $282 per square foot. TDLR closed the project file in February 2026, marking the end of the accessibility review process for this construction.

The scope of work included the construction of a new building, surrounding landscape, sidewalks, and an exterior equipment yard. The design also incorporated a separate truck unloading canopy and a distinct fire pump house. This privately funded project was developed on private land for private use, distinct from municipal or public infrastructure projects in the area.

Construction began in March 2025, with a scheduled completion date of October 2026. The total build window spanned 581 days, which is longer than the county median of 245 days for similar new construction filings.

Project Context and Ownership

Soulbrain TX, LLC is the owner of record for this facility. The company holds two other TDLR-registered projects in Taylor, including an Admin & Warehouse building valued at $10,000,000 and a Guardhouse for $1,000,000. Both previous projects are also marked as closed.

The $10,000,000 estimated cost places this project in the top quarter of new construction filings in Williamson County, where the median cost is $850,000. The $282 per square foot rate is significantly above the county median of $110 per square foot. Colleen G Dement served as the registered accessibility specialist for the project, ensuring compliance with state standards during the design and construction phases.

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 76574 (Taylor)

One email per change. Unsubscribe in one click. Privacy.

T-Project - Production is a New Construction project located at 140 Logistics Loop East, Building 03, Taylor, TX 76574 in Taylor, Texas. The project has an estimated value of $10.0M covering 35,492 sq ft. Soulbrain TX, LLC is the property owner. The project was registered with TDLR on December 4, 2024.

Frequently Asked Questions

Is the production facility at 140 Logistics Loop East open for business?

The TDLR record shows the construction project is closed, but this status only reflects the completion of the accessibility review and building permit process. It does not confirm that the business is open or operating.

Who owns the new production building in Taylor, TX?

Soulbrain TX, LLC is the owner and developer of record. The company also holds two other closed TDLR-registered projects in Taylor, including an admin warehouse and a guardhouse.

What was the total cost of the construction project?

The estimated cost for the new building and surrounding infrastructure was $10,000,000. This figure includes the main structure, landscape, sidewalks, and separate utility buildings.

When did construction start and finish?

Construction started in March 2025. The TDLR closed the project file in February 2026, which marks the end of the official accessibility review process for the construction.

Is the site in a flood zone?

It is designated as zone X on the National Flood Hazard Layer.

What is T-Project - Production?

T-Project - Production is a new construction project at 140 Logistics Loop East, Building 03 in Taylor, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New building and surrounding landscape, sidewalks, exterior equipment yard, separate truck unloading canopy, and separate fire pump house.

Is T-Project - Production open in Taylor?

Construction on T-Project - Production is complete — TDLR records show the project passed its required accessibility inspection in Feb 2026. The building is finished and very likely open.

Where is T-Project - Production located?

T-Project - Production is located at 140 Logistics Loop East, Building 03, Taylor, TX, 76574, in Williamson County.

Who is the owner or developer of T-Project - Production?

Soulbrain TX, LLC is the property owner/developer of record for T-Project - Production, per its TDLR project registration.

How much does T-Project - Production cost and how big is it?

T-Project - Production has an estimated construction value of $10.0M and approximately 35,492 square feet (about $282/sqft), based on its TDLR filing.

Scope of Work

New building and surrounding landscape, sidewalks, exterior equipment yard, separate truck unloading canopy, and separate fire pump house.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

140 Logistics Loop East, Building 03, Taylor, TX, 76574

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Related City Permits

Building permits found at or near this location

1405 WOOLDRIDGE DR

BASE: Installing a backup battery system and additional meter socket.

ActiveElectrical PermitAuxiliary PowerOct 2026
View Details
2026-131675 EP
Base Power
1400 LAVACA ST UNIT 950

7 DAY - This permit is for suite 950 only. This is an office finish out with offices conference rooms phone rooms open off

ActiveBuilding PermitRemodelOct 2026
View Details
2026-138512 BP
HMI Construction Services
1407 SAHARA AVE

Express: Repairs due to fire damage

ActiveBuilding PermitRepairOct 2026
$1
View Details
2026-127868 BP
Austin Fire and Flood LLC
1405 KAREN AVE

ePlan: Residential Expedited Review - New Autofill/Heated Pool w/Spa

ActiveBuilding PermitNewOct 2026
View Details
2026-138515 BP
Paradisa Homes, LLC***MAIN***
1409 W 9TH ST

Express: Foundation repair-installing 12 sonotubes piers and steel piers

ActiveBuilding PermitRepairOct 2026
$1
View Details
2026-138525 BP
Douglas Foundation Repair

Watch all construction in 76574 (Taylor)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.