Project intelligenceTDLR TABS2025008084Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement

101 Gopher Trail, Grand Prairie, TX, 75067

Construction complete · Dec 2024Project Closed

Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement is a renovation/alteration project at 101 Gopher Trail, Grand Prairie, in Dallas County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Dec 2024). The project has an estimated value of $750K across about 15,000 sq ft.

Estimated project value
$750K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
15,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$50/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
3 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Dec 19, 2024102 days across supplied datesMar 31, 2025

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Project closed · TDLR filing

    The project record was closed in TDLR.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    13 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    89 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement

Grand Prairie Independent School District completed a specific mechanical renovation at Grand Prairie High School, located at 101 Gopher Trail in Grand Prairie, Texas. The project, filed as the Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement, involved replacing four existing water source heat pumps with four new rooftop units (RTUs) to serve the main and auxiliary gymnasiums. This renovation/alteration covered 15,000 square feet of the facility.

The estimated cost for this work was $750,000, resulting in a cost of $50 per square foot. This figure is below the Dallas County median of $73 per square foot for similar renovation and alteration filings. While the total project cost sits in the top quarter of the county median for this work type, the scheduled build window of 89 days was close to the county median of 92 days.

Innovative Engineering Group served as the design firm of record for the project. Ross A Thomas was the registered accessibility specialist associated with the filing. The project involved public funds and public land, consistent with school district infrastructure updates in the area.

Project Status and Timeline

The construction start date listed in the filing was January 2025, with a scheduled completion date of March 2025. Although the completion date has passed, the official status is determined by the Texas Department of Licensing and Regulation (TDLR) records. TDLR closed the project file in December 2024, which marks the end of the accessibility review process for this construction. This closure indicates that the regulatory review phase was finalized prior to the scheduled construction window.

Grand Prairie ISD has other TDLR-registered projects in the district, including a $10,800,000 project at Grand Prairie High School and a $4,000,000 project at Garcia Elementary School. Innovative Engineering Group is also associated with another $10,800,000 project at Grand Prairie High School. The ZIP code 75067 has a population of about 68,451, with a median household income of $76,630 according to U.S. Census estimates. Dallas County unemployment was 3 percent in August 2026, lower than a year earlier.

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75067 (Grand Prairie)

One email per change. Unsubscribe in one click. Privacy.

Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement is a Renovation/Alteration project located at 101 Gopher Trail,, Grand Prairie, TX 75067 in Grand Prairie, Texas. The project has an estimated value of $750K covering 15,000 sq ft. Grand Prairie Independent School District is the property owner and Innovative Engineering Group is the design firm of record. The project was registered with TDLR on December 19, 2024.

Frequently Asked Questions

What work was performed at Grand Prairie High School?

The project replaced four existing water source heat pumps with four new rooftop units serving the main and auxiliary gymnasiums. This was a renovation/alteration covering 15,000 square feet.

Who is the owner and design firm for this project?

Grand Prairie Independent School District is the owner of record. Innovative Engineering Group is the design firm of record, and Ross A Thomas is the registered accessibility specialist.

What was the estimated cost of the renovation?

The estimated cost was $750,000. This equates to $50 per square foot, which is below the Dallas County median of $73 per square foot for similar renovation filings.

Is the TDLR project file closed?

Yes, TDLR closed the project file in December 2024. This marks the end of the accessibility review process for this construction, even though the scheduled construction window began in January 2025.

Where is the project located?

The project is located at 101 Gopher Trail, Grand Prairie, TX 75067, in Dallas County.

What is Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement?

Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement is a renovation/alteration project at 101 Gopher Trail in Grand Prairie, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Replace 4 existing water source heat pumps with 4 new RTUs serving the main and auxiliary gymnasiums,

Is Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement open in Grand Prairie?

Construction on Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement is complete — TDLR records show the project passed its required accessibility inspection in Dec 2024. The building is finished and very likely open.

Where is Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement located?

Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement is located at 101 Gopher Trail, Grand Prairie, TX, 75067, in Dallas County.

Who is the owner or developer of Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement?

Grand Prairie Independent School District is the property owner/developer of record for Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement, per its TDLR project registration.

Who is the architect or design firm for Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement?

Innovative Engineering Group is the design firm of record for Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement, according to its TDLR filing.

How much does Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement cost and how big is it?

Grand Prairie High School Grand Prairie Fine Arts Academy Gym RTU Replacement has an estimated construction value of $750K and approximately 15,000 square feet (about $50/sqft), based on its TDLR filing.

Scope of Work

Replace 4 existing water source heat pumps with 4 new RTUs serving the main and auxiliary gymnasiums,

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

101 Gopher Trail, Grand Prairie, TX, 75067

Location by street address

Watch all construction in 75067 (Grand Prairie)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Grand Prairie?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.