Final inspection completed, awaiting project closure
Horseshoe Bay Waterfront Bar & Grill Renovation is a Renovation/Alteration project located at 106 Cove West, Horseshoe Bay, TX 78657 in Horseshoe Bay, Texas. The project has an estimated value of $200K covering 1,302 sq ft. Horseshoe Bay Resort Destinations, LLC is the property owner. The project was registered with TDLR on December 20, 2024.
Horseshoe Bay Waterfront Bar & Grill Renovation is a renovation/alteration project at 106 Cove West, Horseshoe Bay, TX 78657 in Horseshoe Bay, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: A renovation of the existing Waterfront Bar & Grill involving only the upper level kitchen and a small portion of the adjacent dining area. The renovation makes no changes to the existing building footprint, structure, exterior enclosureโฆ
Construction on Horseshoe Bay Waterfront Bar & Grill Renovation is complete โ TDLR records show the project passed its required accessibility inspection in May 2026. The building is finished and very likely open.
Horseshoe Bay Waterfront Bar & Grill Renovation is located at 106 Cove West, Horseshoe Bay, TX 78657, Horseshoe Bay, TX, 78657, in Llano County.
Horseshoe Bay Resort Destinations, LLC is the property owner/developer of record for Horseshoe Bay Waterfront Bar & Grill Renovation, per its TDLR project registration.
Horseshoe Bay Waterfront Bar & Grill Renovation has an estimated construction value of $200K and approximately 1,302 square feet (about $154/sqft), based on its TDLR filing.
A renovation of the existing Waterfront Bar & Grill involving only the upper level kitchen and a small portion of the adjacent dining area. The renovation makes no changes to the existing building footprint, structure, exterior enclosure, etc.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Filed
Dec 20, 2024
Review Complete
Feb 11, 2026
Inspection Complete
May 26, 2026
Closed
418d
Review duration
104d
Construction phase