Project intelligenceTDLR TABS2025008712Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements in Duncanville, TX

900 W. Camp Wisdom Road, Duncanville, TX, 75116

Opening ~Oct 2027Review Complete

N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements is a renovation/alteration project at 900 W. Camp Wisdom Road, Duncanville, in Dallas County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Oct 2027. The project has an estimated value of $6.0M across about 177,483 sq ft.

Estimated project value
$6.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
177,483 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$34/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
2y 7mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jan 3, 20251,029 days across supplied datesOct 29, 2027

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    88 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    941 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements

The City of Duncanville is reconstructing N. Cedar Ridge Drive, a project valued at $6,026,022 that covers 177,483 sq ft. This major roadway improvement is located in the 900 W. Camp Wisdom Road area of Duncanville, TX 75116. The work involves a complete renovation and alteration of the street infrastructure between W. Camp Wisdom Road and Middale Road.

Dunaway Associates, LLC serves as the design firm of record for this initiative. The scope of work is extensive, including drainage, water, sewer, signage, pavement markings, illumination, and traffic signal improvements. These upgrades are designed to enhance the safety and functionality of the corridor within Dallas County. The project is registered with the Texas Department of Licensing and Regulation (TDLR) under the accessibility program.

Project Timeline and Status

TDLR completed the plan review process in January 2025, marking the formal approval stage for the construction plans. Construction is scheduled to begin in April 2025. The filing indicates that the project is scheduled to finish in October 2027. This timeline reflects a substantial build window of 941 days, which is longer than the county median of 92 days for similar renovation and alteration filings. The extended duration is consistent with the complexity of subsurface utility work and full street reconstruction.

The estimated cost of $6,026,022 places this project above the median estimated cost for renovation and alteration filings in Dallas County. The median cost for comparable projects is $250,000, with the middle half ranging from $121,000 to $595,415. Despite the higher total cost, the cost per square foot is $34, which is below the county median of $73 per square foot. This discrepancy highlights the different nature of linear roadway projects compared to building renovations, where square footage does not directly correlate with material and labor intensity in the same way.

Regional Context and Ownership

The City of Duncanville has three other TDLR-registered projects totaling $10,265,000, including the Duncanville Fire Station No. 1 and the East Danieldale Road renovation. Dunaway Associates, LLC has six other registered projects totaling $49,157,361, ranging from the Cook Children's 7th Ave Garage to the Trinity Park and Fort Worth Botanic Gardens. The project is funded by public funds, public land, or is a Federally funded roadway project, ensuring it meets specific regulatory and accessibility standards.

Kimberly J Goss is the registered accessibility specialist associated with this filing. The project is situated in a ZIP code with a population of about 19,780 and a median household income of $60,835. The Dallas County unemployment rate was 3 percent in August 2026, lower than a year earlier. The TDLR status for this project is Review Complete, confirming that all necessary pre-construction approvals have been secured.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75116 (Duncanville)

One email per change. Unsubscribe in one click. Privacy.

N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements is a Renovation/Alteration project located at 900 W. Camp Wisdom Road, Duncanville, TX 75116 in Duncanville, Texas. The project has an estimated value of $6.0M covering 177,483 sq ft. City of Duncanville is the property owner and Dunaway Associates, LLC is the design firm of record. The project was registered with TDLR on January 3, 2025.

Frequently Asked Questions

When is the Cedar Ridge Drive reconstruction scheduled to finish?

The project is scheduled to finish in October 2027. Construction is set to start in April 2025, following the completion of plan review in January 2025. This timeline provides a clear window for the duration of the roadway and utility work.

Who is the design firm for this Duncanville street project?

Dunaway Associates, LLC is the design firm of record. The City of Duncanville is the owner and developer of record. Kimberly J Goss is the registered accessibility specialist listed in the TDLR filing for this specific project.

What is the estimated cost of the Cedar Ridge Drive renovation?

The estimated cost is $6,026,022. This figure is above the median cost for renovation and alteration projects in Dallas County, which is $250,000. The project covers 177,483 sq ft of roadway and subsurface utility improvements.

Is the project open to the public?

The TDLR record indicates the project status is Review Complete. Construction is scheduled to begin in April 2025 and finish in October 2027. The record does not provide information regarding public access during the construction phase.

What specific improvements are included in the scope of work?

The scope includes drainage, water, sewer, signage, pavement markings, illumination, and traffic signal improvements. The work covers the section of Cedar Ridge Drive between W. Camp Wisdom Road and Middale Road in Duncanville.

What is N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements?

N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements is a renovation/alteration project at 900 W. Camp Wisdom Road in Duncanville, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Reconstructing Cedar Ridge Drive between W. Camp Wisdom Road and Middale Road, including drainage, water, sewer, signage, pavement markings, illumination, and traffic signal improvements

Is N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements open in Duncanville?

N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements is still under construction in Duncanville, TX, with an estimated completion of Oct 2027 according to its TDLR registration.

Where is N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements located?

N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements is located at 900 W. Camp Wisdom Road, Duncanville, TX, 75116, in Dallas County.

Who is the owner or developer of N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements?

City of Duncanville is the property owner/developer of record for N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements, per its TDLR project registration.

Who is the architect or design firm for N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements?

Dunaway Associates, LLC is the design firm of record for N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements, according to its TDLR filing.

How much does N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements cost and how big is it?

N. Cedar Ridge Drive Street Reconstruction and Subsurface Utility Improvements has an estimated construction value of $6.0M and approximately 177,483 square feet (about $34/sqft), based on its TDLR filing.

Scope of Work

Reconstructing Cedar Ridge Drive between W. Camp Wisdom Road and Middale Road, including drainage, water, sewer, signage, pavement markings, illumination, and traffic signal improvements

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

900 W. Camp Wisdom Road, Duncanville, TX, 75116

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 75116 (Duncanville)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Duncanville?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.