SHSU Bowers Stadium Press Box Replacement in Huntsville, TX
620 Bowers Boulevard, Huntsville, TX, 77340
SHSU Bowers Stadium Press Box Replacement is a renovation/alteration project at 620 Bowers Boulevard, Huntsville, in Walker County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Oct 2026). The project has an estimated value of $44.9M across about 43,390 sq ft.
- Estimated project value
- $44.9M
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 43,390 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $1.03K/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 1y 6mo
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
5 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordReview complete · TDLR filing
The filing records completion of the accessibility review.
Same day as the preceding date shown.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
44 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
525 days after the preceding date shown.
Source: TDLR filing
View source recordInspection complete · TDLR filing
The filing records completion of the accessibility inspection.
65 days after the preceding date shown.
Source: TDLR filing
View source record
📰About SHSU Bowers Stadium Press Box Replacement
The Sam Houston State University Bowers Stadium Press Box Replacement in Huntsville has passed its final TDLR accessibility inspection. The project, filed in January 2025, is marked as Inspection Complete. This confirms that the construction phase is finished and the building meets state accessibility standards.
Scope and Scale
The work involved demolishing the existing press box structure and constructing a new, expanded five-story building. The filing describes the scope as related stadium site upgrades. The total square footage of the new facility is 43,390 sq ft. The estimated cost for this renovation and alteration was $44,866,000.
Project Details
The owner of record is Sam Houston State University. The design firm of record is Page Southerland Page. The registered accessibility specialist for this project is William T. Winning. The project is located at 620 Bowers Boulevard in Walker County. It involves public funds and public land.
Timeline and Status
Plan review was completed in January 2025. Construction started in February 2025. The scheduled completion date on the filing was August 2026. The final inspection took place in October 2026. The TDLR status is now Inspection Complete. This project is one of several major developments associated with the university in the area.
Context and Comparison
This project is significantly larger and more costly than the median renovation in Walker County. The median estimated cost for similar filings in the county is $237,405, while this project is in the top quarter. The median size is 3,924 sq ft, compared to the 43,390 sq ft here. The cost per square foot is $1,034, which is above the county median of $70 per square foot. The scheduled build window of 525 days is longer than the county median of 122 days.
Inspection Complete
Final inspection completed, awaiting project closure
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 77340 (Huntsville)
One email per change. Unsubscribe in one click. Privacy.
SHSU Bowers Stadium Press Box Replacement is a Renovation/Alteration project located at 620 Bowers Boulevard, Huntsville, TX 77340 in Huntsville, Texas. The project has an estimated value of $44.9M covering 43,390 sq ft. Sam Houston State University is the property owner and Page Southerland Page is the design firm of record. The project was registered with TDLR on January 13, 2025.
Frequently Asked Questions
Is the Bowers Stadium Press Box replacement finished?
Yes, the project passed its final TDLR accessibility inspection in October 2026. The TDLR status is listed as Inspection Complete, indicating construction is finished.
Who designed the new press box building?
The design firm of record for the Sam Houston State University project is Page Southerland Page. They are responsible for the architectural plans for the new five-story structure.
How much did the project cost?
The estimated cost for the demolition and replacement of the press box was $44,866,000. This figure is significantly higher than the median cost for renovation projects in Walker County.
What is the size of the new building?
The new expanded press box building is 43,390 square feet. It is a five-story structure replacing the previous facility at Bowers Stadium.
When did construction start?
Construction started in February 2025, following the completion of plan review in January 2025. The project was registered with TDLR in January 2025.
What is SHSU Bowers Stadium Press Box Replacement?
SHSU Bowers Stadium Press Box Replacement is a renovation/alteration project at 620 Bowers Boulevard in Huntsville, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: demolish and replace existing press box building with new expanded 5 story building and related stadium site upgrades
Is SHSU Bowers Stadium Press Box Replacement open in Huntsville?
Construction on SHSU Bowers Stadium Press Box Replacement is complete — TDLR records show the project passed its required accessibility inspection in Oct 2026. The building is finished and very likely open.
Where is SHSU Bowers Stadium Press Box Replacement located?
SHSU Bowers Stadium Press Box Replacement is located at 620 Bowers Boulevard, Huntsville, TX, 77340, in Walker County.
Who is the owner or developer of SHSU Bowers Stadium Press Box Replacement?
Sam Houston State University is the property owner/developer of record for SHSU Bowers Stadium Press Box Replacement, per its TDLR project registration.
Who is the architect or design firm for SHSU Bowers Stadium Press Box Replacement?
Page Southerland Page is the design firm of record for SHSU Bowers Stadium Press Box Replacement, according to its TDLR filing.
How much does SHSU Bowers Stadium Press Box Replacement cost and how big is it?
SHSU Bowers Stadium Press Box Replacement has an estimated construction value of $44.9M and approximately 43,390 square feet (about $1.03K/sqft), based on its TDLR filing.
Scope of Work
demolish and replace existing press box building with new expanded 5 story building and related stadium site upgrades
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
620 Bowers Boulevard, Huntsville, TX, 77340
Explore the supplied address
A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.
Related Projects
Same Owner
$462.5M totalWatch all construction in 77340 (Huntsville)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Huntsville?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.