Project intelligenceTDLR TABS2025009962New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

MVISD Middle School #3 in Medina, TX

W. Montgomery and Straus Medina, Medina, TX, 78252

Opening ~Apr 2027Review Complete

MVISD Middle School #3 is a new construction project at W. Montgomery and Straus Medina, Medina, in Bexar County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Apr 2027. The project has an estimated value of $80.7M across about 172,284 sq ft.

Estimated project value
$80.7M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
172,284 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$469/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
2y 1mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jan 21, 2025822 days across supplied datesApr 23, 2027

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    86 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    736 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About MVISD Middle School #3

MVISD Middle School #3 is a new 172,284 sq ft educational facility located at the intersection of W. Montgomery and Straus Medina in Medina, TX 78252. The project is registered with the Texas Department of Licensing and Regulation (TDLR) and is scheduled to finish in April 2027. The structure is designed to serve 1,200 students for the Medina Valley ISD district.

The total estimated cost for this new construction is $80,746,107. This valuation places the project in the top quarter of new construction filings in Bexar County, significantly above the county median of $600,000. The cost per square foot stands at $469, which is above the Bexar County median of $115 per square foot for similar new construction projects.

Project Team and Timeline

VLK Architects serves as the design firm of record for the project. The registered accessibility specialist is Peter F Grojean. TDLR completed the plan review process in January 2025. Construction work is set to begin in April 2025, establishing a scheduled build window of 736 days. This duration is longer than the Bexar County median build time of 207 days for comparable new construction filings.

The project involves public funds and public land. Medina Valley ISD is the owner and developer of record. The district has six other TDLR-registered projects totaling $281,690,000, including a new high school in San Antonio and an AG-JROTC building in Castroville. VLK Architects has six other registered projects totaling $65,050,000, including a new collegiate academy in Fort Worth and a maintenance warehouse in White Settlement.

The local area profile for ZIP code 78252 indicates a population of about 18,256 residents. The median household income is $79,635, and the median owner-occupied home value is $242,000. The housing stock in this area is predominantly owner-occupied. The Bexar County unemployment rate was 4.8 percent in June 2026, which is higher than a year earlier.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78252 (Medina)

One email per change. Unsubscribe in one click. Privacy.

MVISD Middle School #3 is a New Construction project located at W. Montgomery and Straus Medina, Medina, TX 78252 in Medina, Texas. The project has an estimated value of $80.7M covering 172,284 sq ft. Medina Valley ISD is the property owner and VLK Architects is the design firm of record. The project was registered with TDLR on January 21, 2025.

Frequently Asked Questions

When is the construction scheduled to end?

The project is scheduled to finish in April 2027. Construction is set to start in April 2025, creating a two-year build window as recorded in the TDLR filing.

Who is the architect for MVISD Middle School #3?

VLK Architects is the design firm of record for this project. The registered accessibility specialist listed in the filing is Peter F Grojean.

How much does the new school cost?

The estimated cost is $80,746,107. This figure is above the Bexar County median for new construction, placing it in the top quarter of filings by cost.

Is the school open for classes?

The TDLR record indicates the project is under new construction with a completion date in April 2027. There is no information in the filing regarding operational status or opening dates.

Who owns the property?

Medina Valley ISD is the owner and developer of record. The project involves public funds and public land within the Medina Valley ISD district.

What is MVISD Middle School #3?

MVISD Middle School #3 is a new construction project at W. Montgomery and Straus Medina in Medina, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New 1200 student Middle School building for Medina Valley ISD.

Is MVISD Middle School #3 open in Medina?

MVISD Middle School #3 is still under construction in Medina, TX, with an estimated completion of Apr 2027 according to its TDLR registration.

Where is MVISD Middle School #3 located?

MVISD Middle School #3 is located at W. Montgomery and Straus Medina, Medina, TX, 78252, in Bexar County.

Who is the owner or developer of MVISD Middle School #3?

Medina Valley ISD is the property owner/developer of record for MVISD Middle School #3, per its TDLR project registration.

Who is the architect or design firm for MVISD Middle School #3?

VLK Architects is the design firm of record for MVISD Middle School #3, according to its TDLR filing.

How much does MVISD Middle School #3 cost and how big is it?

MVISD Middle School #3 has an estimated construction value of $80.7M and approximately 172,284 square feet (about $469/sqft), based on its TDLR filing.

Scope of Work

New 1200 student Middle School building for Medina Valley ISD.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

W. Montgomery and Straus Medina, Medina, TX, 78252

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 78252 (Medina)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.