Project intelligenceTDLR TABS2025010812Renovation/Alteration
Funding type

This project is privately funded, on private land for private use.

MH Pearland Hospital NM/CT Equipment Replacement

16100 South Freeway, Level 2, Pearland, TX, 77584

Construction complete · Jan 2026Project Closed

MH Pearland Hospital NM/CT Equipment Replacement is a renovation/alteration project at 16100 South Freeway, Level 2, Pearland, in Brazoria County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jan 2026). The project has an estimated value of $160K across about 446 sq ft.

Estimated project value
$160K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
446 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$359/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
6 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jan 31, 2025356 days across supplied datesJan 22, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    52 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    186 days after the preceding date shown.

    Source: TDLR filing

    View source record
  5. Project closed · TDLR filing

    The project record was closed in TDLR.

    118 days after the preceding date shown.

    Source: TDLR filing

    View source record

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77584 (Pearland)

One email per change. Unsubscribe in one click. Privacy.

MH Pearland Hospital NM/CT Equipment Replacement is a Renovation/Alteration project located at 16100 South Freeway, Level 2, Pearland, TX 77584 in Pearland, Texas. The project has an estimated value of $160K covering 446 sq ft. Memorial Hermann Health System is the property owner and THR3E Design is the design firm of record. The project was registered with TDLR on January 31, 2025.

Frequently Asked Questions

What is MH Pearland Hospital NM/CT Equipment Replacement?

MH Pearland Hospital NM/CT Equipment Replacement is a renovation/alteration project at 16100 South Freeway, Level 2 in Pearland, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: This project consists of the build-out of an existing white-box Shell Space with the installation of medical equipment with no change to Exterior Walls, Demising Walls, or Entry/Exit Access to the Existing Space

Is MH Pearland Hospital NM/CT Equipment Replacement open in Pearland?

Construction on MH Pearland Hospital NM/CT Equipment Replacement is complete — TDLR records show the project passed its required accessibility inspection in Jan 2026. The building is finished and very likely open.

Where is MH Pearland Hospital NM/CT Equipment Replacement located?

MH Pearland Hospital NM/CT Equipment Replacement is located at 16100 South Freeway, Level 2, Pearland, TX, 77584, in Brazoria County.

Who is the owner or developer of MH Pearland Hospital NM/CT Equipment Replacement?

Memorial Hermann Health System is the property owner/developer of record for MH Pearland Hospital NM/CT Equipment Replacement, per its TDLR project registration.

Who is the architect or design firm for MH Pearland Hospital NM/CT Equipment Replacement?

THR3E Design is the design firm of record for MH Pearland Hospital NM/CT Equipment Replacement, according to its TDLR filing.

How much does MH Pearland Hospital NM/CT Equipment Replacement cost and how big is it?

MH Pearland Hospital NM/CT Equipment Replacement has an estimated construction value of $160K and approximately 446 square feet (about $359/sqft), based on its TDLR filing.

Scope of Work

This project consists of the build-out of an existing white-box Shell Space with the installation of medical equipment with no change to Exterior Walls, Demising Walls, or Entry/Exit Access to the Existing Space

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

16100 South Freeway, Level 2, Pearland, TX, 77584

Location by street address

Watch all construction in 77584 (Pearland)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Pearland?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.