SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL in Von Ormy, TX

4495 Verano Pkwy BLDG 200, Von Ormy, TX, 78073

Construction complete · Mar 2026Inspection Complete

SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL is a renovation/alteration project at 4495 Verano Pkwy BLDG 200, Von Ormy, in Bexar County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Mar 2026). The project has an estimated value of $257K across about 200 sq ft.

Estimated project value
$257K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
200 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$1.28K/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
8 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Feb 6, 2025398 days across supplied datesMar 11, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    54 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    252 days after the preceding date shown.

    Source: TDLR filing

    View source record
  5. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    92 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL

The Swisd Fencing Project at Resnik Middle School in Von Ormy is complete. The project passed its final TDLR accessibility inspection in March 2026, confirming that construction activities have concluded. The work involved demolishing and replacing existing fencing and gates to secure the campus at 4495 Verano Pkwy BLDG 200.

This renovation/alteration project was registered with the Texas Department of Licensing and Regulation (TDLR) in February 2025. Plan review was completed in the same month. Construction was scheduled to begin in April 2025, with a planned completion date of December 2025. The final inspection occurred in March 2026, following the scheduled timeline.

The estimated cost for the project was $256,940. The scope of work covered 200 square feet, resulting in a cost per square foot of $1,285. The owner of record is the Board of Trustees of Southwest ISD. Jessica Trevino Hamm served as the registered accessibility specialist for this filing.

Project Context

In Bexar County, the median estimated cost for renovation/alteration filings is $250,000. This project’s cost is close to that county median. The median size for such projects is 4,115 square feet, while this project was significantly smaller at 200 square feet. The median cost per square foot in the county is $85, whereas this project’s rate was above that figure at $1,285.

The scheduled build window for this project was 252 days, which is longer than the county median of 103 days. Southwest ISD has three other TDLR-registered projects totaling $966,910, including Southwest Legacy HS, Medio Creek Elementary, and Spicewood Elementary, all of which have completed their inspections.

According to U.S. Census ACS 2023 estimates, the Von Ormy ZIP code 78073 has a population of about 9,510. The median household income is $65,342, and the median owner-occupied home value is $139,600. The area is predominantly owner-occupied housing. Bexar County’s unemployment rate was 4.6 percent in August 2026, lower than the rate a year earlier.

Inspection Complete

Final inspection completed, awaiting project closure

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78073 (Von Ormy)

One email per change. Unsubscribe in one click. Privacy.

SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL is a Renovation/Alteration project located at 4495 Verano Pkwy BLDG 200, Von Ormy, TX 78073 in Von Ormy, Texas. The project has an estimated value of $257K covering 200 sq ft. BOARD OF TRUSTEES OF SOUTHWEST ISD is the property owner. The project was registered with TDLR on February 6, 2025.

Frequently Asked Questions

Is the fencing project at Resnik Middle School finished?

Yes, the project is complete. It passed its final TDLR accessibility inspection in March 2026, confirming that the demolition and installation of new fencing and gates are done.

Who owns the Resnik Middle School facility?

The owner of record is the Board of Trustees of Southwest ISD. The facility is located at 4495 Verano Pkwy BLDG 200 in Von Ormy, Texas.

What was the estimated cost of the fencing renovation?

The estimated cost was $256,940. This figure covers the demolition of existing structures and the installation of new fencing and gates to secure the campus.

When did construction on the fencing project start?

Construction was scheduled to start in April 2025. The project was registered with TDLR in February 2025, and plan review was completed in that same month.

Is the school open to the public?

The TDLR record confirms the construction project is complete, but it does not provide information regarding the school's operating hours or public access status.

What is SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL?

SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL is a renovation/alteration project at 4495 Verano Pkwy BLDG 200 in Von Ormy, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: DEMOLISH AND REPLACE EXISTING FENCING/GATES AND INSTALL NEW FENCING/GATES TO SECURE CAMPUS.

Is SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL open in Von Ormy?

Construction on SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL is complete — TDLR records show the project passed its required accessibility inspection in Mar 2026. The building is finished and very likely open.

Where is SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL located?

SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL is located at 4495 Verano Pkwy BLDG 200, Von Ormy, TX, 78073, in Bexar County.

Who is the owner or developer of SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL?

BOARD OF TRUSTEES OF SOUTHWEST ISD is the property owner/developer of record for SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL, per its TDLR project registration.

How much does SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL cost and how big is it?

SWISD FENCING PROJECT - RESNIK MIDDLE SCHOOL has an estimated construction value of $257K and approximately 200 square feet (about $1.28K/sqft), based on its TDLR filing.

Scope of Work

DEMOLISH AND REPLACE EXISTING FENCING/GATES AND INSTALL NEW FENCING/GATES TO SECURE CAMPUS.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

4495 Verano Pkwy BLDG 200, Von Ormy, TX, 78073

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 78073 (Von Ormy)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Von Ormy?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.